Biogas plant Radovesice, Czech Republic
- BGP 844 kW
- Secondary fermenter volume of 3 450 m3, fermentation temperature 41°C
- The crust thickness of 3 m consisting of unfermented maize silage
- Application of the preparates on 21st January2019 – in process (stirrers reparation)
Biogas plant Slativa Czech Republic
- BGP 549 kW
- Primary fermenter volume of 2 090 m3, fermentation temperature 42°C
- The crust thickness of 2 m consisting mainly of unfermented straw
- The total time of dissolution of the crust: 4 weeks
Biogas plant Velešovice, Czech Republic
- BGP 637 kW
- Final digestate fermenter with a capacity of 5,000 m3
- The crust thickness of 1,5 m consisting mainly of leftovers of unfermented silage of the GPS
- The total time of crust decomposition: 6 months - product dosage by the main fermenter
Biogas plant Turá Lúka, Czech Republic
- BGP 1 MW
- Primary fermenter volume of 4 000 m3, fermentation temperature 40°C
- The crust thickness of 1 m consisting mainly of unfermented maize and grass silages
- The total time of crust decomposition: 2 weeks
Biogas plant Opava-Kylešovice, Czech Republic
- BGP 550 kW
- Secondary fermenter volume of 2 700 m3, fermentation temperature 43°C
- The crust thickness of 2 – 3 m, consisting mainly of unfermented straw
- The total time of dissolution of the crust: 4 weeks
Biogas plant Smolinské, Slovakia
- BGP 1,0 MW
- Secondary fermenter volume of 2 700 m3 fermentation temperature 42°C
- The crust thickness of 3 – 5 m, consisting mainly of unfermented maize silage, grass silage and straw
- The total time of dissolution of the crust: 5 weeks
Biogas plant Novosedly, Czech Republic
- BGP 600 kW
- Primary fermenter volume of 2 700 m3, fermentation temperature 42°C
- The crust thickness of 0,5 m consisting mainly of unfermented grass silage